Trade Resources Industry Views Adria Steel Plans to Start Its New Melt Shop in The Middle of January 2013

Adria Steel Plans to Start Its New Melt Shop in The Middle of January 2013

It is reported that Croatian rebar mini-mill Adria Steel has announced that the company plans to start its new melt shop in the middle of January 2013.The company has designed the new melt shop with annual production capacity approximately 200,000 tons.Meanwhile,the operation hours will divide into two shifts for 24 hours production cycle.The company will plan to upgrade facility includes electric arc furnace by installing filtering and de-dusting equipment.In addition,the company is optimizing to see the steel market to be improved in 2013 and it will also guide the company's sales to another level.

Source: http://www.yieh.com/2.2.01.01stainlesssteelnews.aspx?no=62379&division=A9