Four related new national standards (hereinafter referred to as "new standard") regarding boxes and enclosures for electrical accessories for household and similar fixed electrical installations have been published, details are listed as below:
In order to ensure the smooth progress of standard version change and the continuous effectiveness of certification results, in accordance with CNCA [2010] No. 2 notice "Notice of Requirements of New Standard for Compulsory Certification of Boxes and Enclosures for Electrical Accessories for Household and Similar Fixed Electrical Installations", principles and procedures of the standard version change are published as follows:
No. |
Name of Standard |
Standard |
Release Date |
Effective Date |
Deadline for Version Transfer |
1 |
Boxes and enclosures for electrical accessories for household and similar fixed electrical installations - Part 1: General Requirements |
GB17466.1-2008 |
30 December 2008 |
1 February 2010 |
1 February 2011 |
2 |
Boxes and enclosures for electrical accessories for household and similar fixed electrical installations - Part 21: Particular requirements for boxes and enclosures with provision for suspension means |
GB17466.21-2008 |
30 December 2008 |
1 February 2010 |
1 February 2011 |
3 |
Boxes and enclosures for electrical accessories for household and similar fixed electrical installations - Part 23: Particular requirements for floor boxes and enclosures |
GB17466.23-2008 |
30 December 2008 |
1 February 2010 |
1 February 2011 |
4 |
Boxes and enclosures for electrical accessories for household and similar fixed electrical installations - Part 24:Particular requirements for enclosures for housing protective devices and similar power consuming devices |
GB17466.24-2008 |
30 December 2008 |
1 February 2010 |
1 February 2011 |
.I. Principles of Standard Version Change
i. As of the promulgation date and before the new standard is officially carried out, applicants could freely choose the new standard or standard GB17466-1998 (hereinafter referred to as "old standard") for certification application (if the old standard is chosen, sufficient time should be set apart to ensure that the approval certification could be obtained before the new standard is officially carried out). As of 1 February 2010, only the new standard will be adopted for certification.
ii. For those products that have obtained the compulsory authentication certificate, holders of old authentication certificate should submit the standard version change requisition to CQC after the new standard is released and before the next follow-up inspection is carried out. And upon completion of an inspection according the standard difference with satisfactory results, a new authentication certificate shall be issued in accordance with the new standard. Transfer of old authentication certificates will be completed by 1 February 2011, if those certificates were not transferred on time, they would be suspended; If they failed to be replaced before 1 May 2011, they would be disqualified by CQC.
iii. For those certified products in different time-series, which could have merged into one unit, will be processed as one single unit during the supplementary test.
II. Procedures of Standard Version Change
A. Application of Standard Version Change
i. Main Steps
Step 1: Applicants log on CQC website (www.cqc.com.cn) by using their own username and passcode;
Step 2: Click "Fill out the Certification Requisition" on the left side of the screen;
Step 3: Click "Fill out CCC Change Requisition" under "China Compulsory Certification (CCC)";
Step 4: Choose "02 - Circuit Switches and Protection or Electrical Appliances Connection Devices", and then choose "0206 - Enclosures for Electrical Accessories for Household and Similar Fixed Electrical Installations";
Step 5: Accurately fill out the applying certificate number and its corresponding CCC testing report number for those apply for certificate transfer;
Step 6: Fill out the following fundamental information: name of applicant, name of manufacturer, name of plant and address, product name and specification etc;
Step 7: Please choose item 12 to fill out additional information of authentication application: the national standards, technical rules or authentication implementing rules, which the product certification is based on, have changed. Taking boxes and enclosures with provision for suspension means for example, changing items should be filled out like this: before standard version change: GB17466-1998, and after standard version change: GB17466.1-2008 and GB17466.21-2008.
ii. Notes for Application
(1) Both a test and a testing report are required in this standard version change, therefore, blanket request is not acceptable. Applicants please do not fill out multiple certificate numbers in Step 5;
(2) ODM Certificate
a. ODM Certificate holders must communicate with original authentication certificate holders to ensure timely transfer request. Transfer request for ODM certificates should be submitted to CQC within one month after original certificate holders obtain their new authentication certificates.
b. New ODM Certificate application will not be accepted before the original certificate finishes its standard version change. For those products that have applied for ODM, but have not obtained the certificate, process of those applications will be suspended. ODM applications will be continued to process when standard version change of the original certificate is finished, application materials are revised and supplemented and samples that are qualified for the new standard are submitted to inspection bodies for a new report.
c. The agreement should be proposed along with ODM Certificate during the standard version change, and the agreement should meet the requirement of "Notice of Requirements of ODM Original Entrusted Agreement" (Please refer to CQC website, published on 28 November 2007).
d. ODM supplemental requirements should be implemented in accordance with CNCA [2009] No. 30 notice "Supplementary Agreement of ODM Model Involved in Implementation Rules of Product Compulsory Certification".
(3) At the same time when certificate holders apply for standard version change, they could also apply for adding other changing items, for example, adding product specifications etc. However, applicants please specify in step 6 and step 7.
B. Acceptance of Application
In principle, each CCC Certificate should be regarded as one application unit, and please fill in one requisition for each version transfer.
C. Materials and Requirements for Standard Version Change
i. Materials Submitted to CQC
No. |
Name of Application Materials |
Number of Copies |
Requirements |
Remark |
1 |
Transfer Application for CCC Certification |
One Copy |
Original copy. The original shall be signed by the head of unit and bear the business seal. |
Two pages |
2 |
Report of Product Description |
One Copy |
Original copy. The original shall be signed by the head of unit and bear the business seal. |
Four pages |
3* |
Original Certificate |
One Copy |
Original Certificate (Chinese and English) |
|
4 |
Copy of Company Business License |
Once Copy |
Photocopy. The photocopy shall bear the business seal of the application company. |
|
5 |
Copy of Organizational Code Certificate |
One Copy |
Photocopy. The photocopy shall bear the business seal of the application company. |
|
6 |
Effective Factory Inspection Report or Supervision and Inspection Report |
One Copy |
Photocopy The photocopy shall bear an across-page seal of the application company. |
|
7 |
ODM Agreement |
One Copy |
Original Copy The Original copy shall meet the requirements of "Notice of Requirements of ODM Original Entrusted Agreement". |
Applicable only to ODM certificate |
8 |
Other Required Documents |
|
|
|
*: Original certificate is required to be provided for transfer application. In order not to influence the use of certificate during the testing period, the certificate could be delivered directly to the CQC engineer after the test and before the conformity assessment. |
ii. Materials Submitted to the Inspecting Authority
No. |
Name of Application Materials |
Number of Copies |
Requirements |
Remark |
1 |
Transfer Application for CCC Certification |
One copy |
Original copy The original shall be signed by the head of company and bear the business seal, |
Two pages |
2 |
Report of Product Description |
One copy |
Original copy The original shall be signed by the head of company and bear the business seal |
Four pages |
3 |
Copy of Company Business License |
One copy |
Photocopy. The photocopy shall bear the business seal of the application company. |
|
4 |
Copy of Organizational Code Certificate |
One copy |
Photocopy. The photocopy shall bear the business seal of the application company. |
|
5 |
ODM Agreement |
One copy |
Original copy The Original copy shall meet the requirements of "Notice of Requirements of ODM Original Entrusted Agreement". |
Applicable only to ODM certificate |
6 |
Other Required Documents |
|
|
D. Variation Test of Standard Version Change