Trade Resources Industry Views First Solar Has Been Granted a PPA From The New Mexico Public Regulatory Commission

First Solar Has Been Granted a PPA From The New Mexico Public Regulatory Commission

First Solar Inc of Tempe, AZ, USA, which manufactures thin-film photovoltaic (PV) modules based on cadmium telluride (CdTe) as well as providing engineering, procurement & construction (EPC) services, has been granted a power purchase agreement (PPA) from the New Mexico Public Regulatory Commission, clearing the way for First Solar to begin construction on the state's largest solar power plant to be located on State Trust Land in Luna County. The PPA will provide El Paso Electric Power with 50MW of solar energy for 25 years.

"This 50 megawatt solar power project will provide about 300 jobs during the construction phase, which is a huge boost to New Mexico's ailing construction industry, and it will provide a constant stream of revenue for our public schools, universities and hospitals," said State Land Commissioner Ray Powell. "This project will provide clean, efficient solar power to El Paso Electric service territory customers, and the lease payments could generate as much as $40 million for state land trust beneficiaries over the 40-year term of the lease."

The solar array will realize significant water savings over gas-fired or coal-fired generating plants and will have zero air emissions. The proposed Macho Springs solar power plant will generate enough clean energy to power more than 18,000 average New Mexico homes, which use about 669 kilowatt hours of electricity per month. The project will displace more than 40,000 metric tons of CO2, the equivalent of taking 7,500 cars off the road, and will displace water consumption annually (more than 340,000 metric tons).

First Solar has submitted its final development plan that provides a site plan and specific mitigation plans and strategies, and is obtaining various construction permits. Once approved, construction is expected to begin in July.

El Paso Electric Company will purchase the entire output power from the Macho Springs solar power project through a purchase power agreement with First Solar. This project was secured by El Paso Electric through an all-source competitive Request for Proposal process conducted in 2011. The project will operate on a commercial lease from the State Land Office on about 500 acres of land at Macho Springs, near Deming. First Solar also has an interconnection agreement with El Paso Electric.

Source: http://www.semiconductor-today.com/news_items/2013/JUN/FIRSTSOLAR_060613.html
Contribute Copyright Policy
First Solar Set to Construct Begin New Mexico's Largest Solar Power Plant