Pemex-Gas and Chihuahua Gas, the subsidiary of Petroquimica Basica said that Tubacero in Mexico would supply the steel pipe to Los Ramones for the first stage of natural gas pipeline project. It is said that the requirement of pipe for the project totals 118 kilometers with the specification of 48" natural gas line pipe. The pipe amounts about USD600 million and will connect Camargo and Los Ramones. After the project completed, it will supply natural gas of 1 billion cubic foot every day. It is estimated that the project would be finished in December of 2014 and would increase the supply quantity to 2 billion cubic foot every day in December of 2015.